Water supply cycle in Hubballi-Dharwad improves significantly
Hubballi
In a major relief to residents of the twin cities, the water supply situation in Hubballi Dharwad has improved significantly, with the supply cycle in several wards reduced from 8-9 days to a fixed five-day schedule. KUIDFC officials overseeing water distribution said improved pressure management and streamlined supply strategies have helped stabilise water distribution across multiple areas with out causing immediate depletion of storage tanks.
According to officials, around eight wards in Old Hubballi are now receiving water once every five days, compared to the earlier cycle of eight to nine days. Similarly, five wards in Amargol and Navanagar have also been brought under the five-day supply schedule. In Dharwad, nine wards are currently benefiting from the improved supply system.
The improvement has also led to a sharp decline in public grievances. Officials said complaint calls related to water supply have dropped drastically, with almost no major complaints received over the past 15 to 20 days. “Earlier, we had to wait for more than a week to receive water, and people used to struggle daily.
Now the five-day schedule has brought great relief to families,” said Saroja Chavana resident of Old Hubballi. Vanamala, a resident from Navanagar said, “The water pressure has improved considerably and the supply has become more predictable. This has reduced stress for households, especially during summer.”
Progress on 24x7 water supply project Officials also shared updates on the ongoing 24x7 continuous water supply project being implemented in the twin cities. Out of the 46 wards identified for conversion from intermittent supply to round-the-clock water supply, work in 23 wards has al ready been completed.
The remaining 23 wards are currently undergoing pipeline linking works and other pending infrastructure development. Before commissioning the system, authorities will conduct hydro tests to identify and prevent any possible leakages in the newly laid pipelines. The entire 24x7 water supply project is expected to be completed by June next year.
Officials further stated that sufficient water reserves are cur rently available in the Malaprabha Reservoir and Neersagar Reservoir reservoirs, with storage levels standing at around 10 TMC and 0.5 TMC respectively. They expressed confidence that there would be no drinking water shortage during the summer season.
The water board is also planning dedicated future pipeline networks to cater to the region’s growing population and rising water demand. A KUIDFC officer said the improvement in supply was the result of coordinated efforts by the water board and field staff. “We have focused on scientific pressure management, better monitoring and timely maintenance works.
Citizens are now experiencing more regular supply, and our aim is to ensure sustainable and efficient water distribution across all wards,” he said.